MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Introduction
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Request for Proposals
Bidding Documents

Consultant Proposal Forms
and Contracts

Construction Standards
Master Planning
PIPS Program
 
Administrative Resources
PMIS/Unifier
Learning Center
CPPM Purchasing

CPPM Home

 

  Home > Active Projects > Plant Growth East Addition

Plant Growth East Addition: BL3 Containment Facility

Plant Growth East Addition

Project Architect
RSP Architects

Construction Manager at Risk
Knutson Construction

Total Square Footage
6,350

Project Cost
$4.95 Million

shim

This project, located at the intersection of Dudley Avenue and Lindig Avenue in the St. Paul campus is planned as an expansion to the recently completed Plant Growth Facility East building, which houses the BL2 Insect Containment Facility. When Plant Growth Facility East was constructed utilities were oversized to meet anticipated future expansion. The proximity of the Plant Pathology research expansion to the present Insect Containment Facility will allow enhanced insect / pathogen studies across both facilities.

The project includes the construction of a containment laboratory and greenhouse space, designed to completely isolate the research work from the exterior environment. Extensive physical and mechanical controls will be required to provide the required isolation. The following spaces will be provided: receiving, laboratory, preparation, equipment and work areas; inoculation, misting, and growth rooms; greenhouse rooms; support spaces, air locks, toilets, showers and dressing rooms. The project will consist of approximately 4,100 gross square feet on the ground floor, 2,100 gross square feet of mechanical basement space and about 150 gross square feet of remodeled existing space.

Project Timeline

Fall 2006 Design Complete
Fall 2006 Construction Begins
Fall 2007 Construction Complete
Winter 2008 Occupancy
 

Current Construction Photos and Project Status

 
Plant Growth East Addition
shim
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
shim

March 2008

All owner provided equipment installed and operational. Construction and commissioning activities are both 100% complete. Full use of facility pending APHIS ceritification scheduled for early May.

 

Past Progress & Photos