MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Home
 

About Capital Planning and Project Management

Introduction
Mission and Values
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
 Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Vendor Information
 Consultant Proposal
 Forms and Contracts
 Construction  Standards
Master Planning
 
Administrative Resources
PIPS
Sustainability
Unifier
 
Administrative Resources
CPPM Intranet Intranet
Unifier Support

CPPM Home

 

  Home > Active Projects >NOvA Far Detector Building

NOvA Far Detector Building

NOvA

Project Architect:
Burns & McDonnell

Construction Manager at Risk:
Adolfson & Peterson, Inc.

 Total Square Footage: 41,000 GSF

Project Cost: $45,139,000  

Other:
All project capital cost is funded by The U.S. Department of Energy

For more detailed information about NOvA, click here.

 

shim

The scope of work consists of two subprojects: Phase I, Road Improvements and Site Preparation, has been previously approved by the Board.  That project includes the upgrade of approximately 3.5 miles of existing logging road to provide all weather access to the Far Detector Building, clearing and grubbing of the building site and the rock excavation for the Detector Enclosure. The excavated rock will be crushed and sized in order to be used as road base and shielding berm.

Phase II is for construction of the 41,000 GSF Far Detector Building.  The building consists of a below grade enclosure (approximately 70 feet wide by 70 feet tall and 350 feet long).  The enclosure will be situated approximately 40 feet into the rock and will have cast-in-place concrete floor slab and walls. The roof of the Detector Enclosure will be a composite construction of precast concrete planks with a cast-in-place concrete topping.  A 0.5 foot deep barite aggregate layer will provide cosmic ray shielding for the Detector Enclosure.  Other features of the Detector Enclosure include cast-in-place concrete support spaces such as Computer Room, Control Room and Electrical Equipment Room. The Detector Enclosure will have four levels of steel access walkways on the west side that lead to exit stairs.

The adjacent, at-grade, Service Building will include a Loading Dock, Office, Toilet, Scintillator Equipment Room, Mechanical Equipment Room and Fire Protection Room.  The Service Building will be a metal sided, structural steel building with a modified bitumen roof membrane.  Adjacent to the Loading Dock is a tanker unloading facility sized to accommodate four (4) trailers and appropriate spill containment.

The mechanical systems for the facility include rooftop HVAC units, sump pumps,ventilation fans and related accessories.  The fire protection system for the facility will be a water mist system with 20,000 gallons of onsite water storage.

Project Timeline

February 2009 Construction Documents Complete
June 2009 Construction Begins
November 2010 Construction Complete
 

Current Construction Photos and Project Status

October 2009

 
NOva
shim
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
     
shim

October 2009

In October the access road to the site was completed. Contractor used crushed rock from the site for the road base. Rock excavation on the building site is 67% completed. Contractor has poured foundation for the Loading Dock portion of the building in October and started structure steel frame erection. They are pushing hard to enclose the building before the cold weather.

The project is very well received and welcomed by local residents and businesses as it brings a good, much needed business for them in the harsh economy.


Past Progress & Photos